Weeks 16 + 17
date: 2025-01-20
What we've been doing
- Accounts functionality has been implemented.
- Live host has Been implemented https://sysenggroup11frontend.ibrahimgabol.com/login
- Semantic Search has been completed, having been integrated with the front end and backend.
- CMS Backend creation and editing of article and events is working
- Elevator Pitch went very well, we successfully delivered a 2-minute presentation of what our project is about
- Implemented Continous Integration, building, linting and tests on backend + frontend
- Updated the MoSCoW list
- reporting page is finished + backend
Evaluation
- We have an updated MoSCoW list and should be on track for most features to be complete, don't see any huge blockers
What we will be doing
- we will finish uploading PDFs on CMS
- connect the events backend to the frontend.
- Continue making progress on our updated Moscow list